Shop Floor Workbench interval based on calendar?

  • 14 January 2020
  • 2 replies
  • 180 views

Userlevel 4
Badge +9

Hi,

 

We are facing the issue where the interval from our Shop Floor Workbench Filters is not looking at the manufacturing calendar.  We have for example an interval of -10 days in the past and 3 days in the future. This is causing issues on the Fridays where users are not able to see the planning for Monday and Tuesday. 

Is there a fix/workaround for this issue?

icon

Best answer by Björn Hultgren 16 January 2020, 11:29

View original

2 replies

Userlevel 7
Badge +23

Hi @Jur 

In early versions, Site was not mandatory in the filter section, so it would have impossible to know what manufacturing calendar to use.

In Apps 10 site is mandatory, hence I agree with you, it would be more useful if the interval related to work days according to the Site Manufacturing Calendar. 

Maybe you can put a support case to IFS requesting this to be fix for coming releases? 

If you need to have it fixed now I believe it must be done as a small customization.

Regards,

Björn

Userlevel 4
Badge +9

@Björn Hultgren , thanks for your feedback and answers. I will definitely create a case regarding this issue.