Solved

Set status of a routing to 'Tentative' from 'Cancelled' status

  • 29 December 2021
  • 2 replies
  • 94 views

Userlevel 3
Badge +6

Is there any way to set status 'Tentative' to a Routing whose status is 'Cancelled'?

We have Routings whose status are 'Cancelled'. We'd like set them to 'Tentative' status for some reason.
Is there any way to do it?

(This is a case that a status before “cancelled” is “Plannable”. We know if it was “Tentative” before cancel, “Review” RMB sets its state “Tentative”.)

 

Using APPS10
Routings tab on Engineering > Routing > Routing

Thank you.
Kazu

icon

Best answer by Björn Hultgren 29 December 2021, 09:06

View original

This topic has been closed for comments

2 replies

Userlevel 7
Badge +23

Unfortunately I think the status will go back to the status it had before it was cancelled. So if it was Plannable before it was Cancelled, it will go back to Plannable after you click Review.

Luckily it should be easy to copy the routing to a new revision in status Tentative!

 

Userlevel 3
Badge +6

Hi Björn,
Thank you for your explanation.
I'll forward it to the customer project team.
Best regards,
Kazu