Schedule operations based on a fixed date

  • April 20, 2022
  • 2 replies
  • 147 views

Forum|alt.badge.img+14

Hi all,

Sometime we have to start an operation on a fixed date. The other operations then have to be rescheduled according to that date. In the example below.

Operation 20 must start 27-05-2022 06:00:00.

The following operations are then rescheduled, but the operation (10) before does not rescheduled . How do we make it do that?

 

Best answer by Björn Hultgren

If you use the rescheduling options available from Manufacturing Visualizer (Enterprise Explorer) or Visual Planning (Aurena), you have the option Compress Operations. If you reschedule operation 20 to start 06:00 on the 27th and select this option, operation 10 would have been backward scheduled to finish 06:00 on the 27th (or whenever the previous work time is).

 

2 replies

Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+25
  • Hero (Employee)
  • 1061 replies
  • Answer
  • April 20, 2022

If you use the rescheduling options available from Manufacturing Visualizer (Enterprise Explorer) or Visual Planning (Aurena), you have the option Compress Operations. If you reschedule operation 20 to start 06:00 on the 27th and select this option, operation 10 would have been backward scheduled to finish 06:00 on the 27th (or whenever the previous work time is).

 


Forum|alt.badge.img+14
  • Author
  • Hero (Partner)
  • 241 replies
  • April 21, 2022

Thanks @Björn Hultgren ,

It was the functionality I was looking for.