Hi All,
Surprisingly, I can’t appear to find any topics on this within the forum.
My client is a food producer of time limited perishable items (such as dairy).
In IEE IFS plans in a day by day format. If you have a multi level structure, say 4 levels, this could potentially mean a 5 day lead time on the Top level component which is not ‘’real world’’.
This all needs to be planned on the same day (all materials are available on site). This doesn’t refer to a situation when a material needs purchased and the lead time to get it in is 10 days.
My question is, Intraday (sameday) Planning is Active in Cloud and covers this scenario. Has there been any work on Intraday in Aurena that can be utilised?
Thanks in advance.