Could someone confirm if we can see shop order load against the “Person” please? I assume we can’t because we connect the labor class to the resource group.  I guess it will be same with production schedule and CRP calculated loads too. Tried to find a documentation to check if there are prerequisites but it was not successful. 

Nav. path -Resource Management\Analysis\Resource Analysis 

 

Unfortunately shop orders are normally not scheduled on a Person level. With APB it is possible to schedule them on Person resources, but I'm not sure whether that load can be analysed in the Resource Analysis window. 