Skip to main content

Hi. We are using the screen Resource Analysis to review manufacturing demand against planned avilable resource but can't work out what the ‘Preliminary demand’ and ‘Planned demand’ is used for?

our graph only shows Shop order, CRP calculated and Absence data (see below).

 

regards

Jamie 

Hi,

I’m sorry for digging out that topic but I’m trying to figure it out as well. Have you found answer to your question?

I’m mostly interested how to show customer demand (coming from plans/schedules only, not orders as they are already visible here) as planned or preliminary demand here in resource analysis.

Is it possible?


 

@olek , does this help at all ?

Demand Status

The column demand status is used in resource management and gets its value by mapping the status from the origin of the source. The demand status can have four different statuses Preliminary, Planned, Committed and Completed.
The following mappings are used to map the origin status from the different sources to the demand status value.

Source

Origin

Origin Status

Demand Status

Human Resources

HR Absence

Registered

Committed

 

 

Partly calculated

Committed

 

 

Calculated

Committed

 

 

Calculation Cancelled

Committed

 

Training events - Event Trainer

Planned Preliminary
    Published Planned
    Confirmed Committed
    Completed Completed

 

Training events - Event Participant

Waiting List

Preliminary

    Waiting Approval Preliminary
    Registered Planned
    Confirmed Committed
    Notified Committed
    Absent Completed
    Attended Completed

Projects

Project Activity

Planned

Planned

 

 

Released

Committed

 

 

Completed

Completed

 

 

Closed

Completed

 

Project Resource Forecast

Preliminary

Preliminary

 

 

Approved

Planned

Service and Asset PM Action Active Planned
  Maintenance Order - Work Task New Planned
    Under preparation Planned
    Prepared

Planned

    Released Committed
    Work Started Committed
    Work done Committed
    Reported Committed
    Finished Committed
  Compatible Unit Confirmed Planned

 


Thanks, I’ve already found that table, unfortunately it doesn’t help much becuase it looks that there’s no possibility to show customer demand from schedules in resource analysis.

 


Reply