Question

Reserve production capacity

  • 22 February 2023
  • 0 replies
  • 22 views

Userlevel 6
Badge +11

Hi,

 

how do you guys block capacity in production, without having shop orders?

 

For example: during a project, you allready know that you will need some capacity in production, but the shop order can’t be made yet. You know for sure you will need the CNC machine, but cannot make the SO yet.

We do want to reserve the capacity in production. We can’t wait untill the SO is ready, as this will delay the project.

 

Thanks!


0 replies

Be the first to reply!

Reply