Is there not any possible way to “Ship WIP To Supplier” for many Order No at once and not - One by one? Etc Report Shop order Lines ?

Hi @EspenB,

Unfortunately, there is no way to achieve your expectation in the standard application. 

Hope my answer helped to clear your doubts. If so be kind enough to mark it as the best answer.


@EspenB Try Outside Op Rpt Level in Outside workcenter or you can set it in the operation level too. You will not need to Ship WIP to Supplier if you set to Purchase Order Arrival, it will auto execute when at PO arrival. 

 


@EspenB Try Outside Op Rpt Level in Outside workcenter or you can set it in the operation level too. You will not need to Ship WIP to Supplier if you set to Purchase Order Arrival, it will auto execute when at PO arrival. 

 

Hi, thank you I will get this tested, thank you very much for sharing!