Question

Project MRP netting hierarchy: why are MTRs created between activities that are already balanced?

  • Oct 29, 2026 1:30 AM UTC
  • 2 replies
  • 40 views

Forum|alt.badge.img+4

Hi all,

The IFS Cloud documentation for Project MRP (About PMRP) gives this netting hierarchy:

  1. Within the demand activity
  2. Within valid project netting groups
  3. Standard inventory

I’m seeing PMRP results that don’t seem to follow step 1, and I’d like to understand how the netting actually works.

Scenario (one project, one site, PMRP run with project-level netting / project PNG)

Activity Demand Supply Date
WF0 none 7 pcs on hand in project inventory (surplus) Available now
WF1 Material Req 10 Released PO line 1: 10 19/02/2027
WF4 Material Req 10 Released PO line 2: 10 Demand 20/05/2027, PO 19/05/2027

WF1 and WF4 are each already balanced by their own PO line. The only excess is the 7 on hand at WF0.

PMRP result (Inventory Part Availability Planning)

  • Planned MTR: WF0 → WF1, qty 7, due 19/02/2027
  • Planned MTR: WF1 → WF4, qty 7, due 20/05/2027

So PMRP moves the WF0 stock into WF1, which pushes 7 of WF1’s own PO quantity into surplus, and then plans a second MTR to move that surplus on to WF4.

Questions

  1. If netting is “within the demand activity” first, why isn’t WF1’s demand covered by WF1’s own PO before PMRP looks at WF0’s stock?
  2. Does PMRP actually net at project/PNG level in date order (earliest supply to earliest demand, regardless of activity) and then create MTRs to rebalance between activities? If so, what does “within the demand activity” mean in practice?
  3. Does pegging or reservation status matter here? The PO lines show Pegged = 0. Would pegging the PO line to the activity demand change the result?
  4. Is this the expected design, or a defect? If it’s expected, what’s the recommended setup to get a single MTR (or none) when activities are already balanced? The options I know of are per-activity PMRP, “Generate MTR for Planning Only” on the PNG, and Excluded Parts.
  5. Second test: I increased WF4’s demand from 10 to 17, so after its own PO line there is a real shortage of 7 at WF4. Following the documented hierarchy, I expected a single MTR from WF0 to WF4 for 7. Instead, PMRP again created two MTRs: WF0 → WF1 for 7 (due 19/02/2027) and WF1 → WF4 for 7 (due 20/05/2027), even though WF1 is fully covered by its own PO. Why doesn’t PMRP transfer WF0’s surplus straight to the activity that’s short?

Version: 26R1

Thanks in advance.

https://www.linkedin.com/in/saman2k1/

2 replies

Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • Nov 24, 2026 4:49 PM UTC

Short answer: the scope of the PMRP job decides where netting happens. A per-project run nets between the activities of the project, whereas a per-activity run nets only within each activity, so cross-activity MTRs from a project-level run are part of how that job works.

The three PMRP jobs

  • Perform Project MRP per Activity: the netting occurs within the activity and not across activities.
  • Perform PMRP per Project PNG: the job runs one project at a time and the netting occurs between the activities of the project.
  • Perform Project MRP per Planned Netting Group: the third scope, which considers the activities within the netting group.

What that means for your example

With project-level netting, surplus project inventory in WF0 sits in the same netting pool as the demands and supplies of WF1 and WF4, which is why transfer MTRs between activities can appear even when each activity looks balanced on its own.

If you want each activity to stand alone, run Perform Project MRP per Activity on the same data and compare the MTRs that come out.

Worth a look: the IFS Cloud documentation for About Project MRP and the PMRP scheduled tasks (Perform PMRP per Project PNG, Perform Project MRP per Activity).

Have you tried the per-activity job on the same project to see whether the MTRs disappear?

Created with the help of Ask Olive.


Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • Nov 24, 2026 5:14 PM UTC

Short answer: in a project PNG run the supply and demand of all the activities in the project are netted together, and any surplus in one activity can meet demand in another through MTRs. So the three-step hierarchy is about where supply can come from, not a rule that each activity is settled against its own PO before anything moves.

A1. Why isn't WF1's demand covered by WF1's own PO first?

The hierarchy (within the demand activity, within valid project netting groups, standard inventory) lists the places supply can be taken from. With netting per project PNG, the calculation considers supply and demand of all the activities in the project at one time, so an excess in one activity can be used for another activity's demand. WF0's 7 on hand is exactly that kind of excess, and the transfer is done with an MTR. Step 1 is not a guarantee that WF1's PO is used up before WF0's stock is looked at.

  • Standard inventory only comes in if the Project/Site tab is set to use standard inventory true surplus, so it is not part of your WF0 case.
  • Which activity's material is reviewed first is controlled by the priority number on the activities within the netting group (each priority number can only be used once per PNG). Check what WF0, WF1 and WF4 have.

A2. Does it net at project/PNG level in date order and then rebalance with MTRs?

The pooling at project/PNG level and the use of MTRs to move the excess between activities is how the job is meant to work. The order between activities follows the priority numbers on the PNG rather than a strict earliest-supply-to-earliest-demand rule. In practice, "within the demand activity" is the first place supply is taken from, but a project PNG run does not stop there if another activity in the same project holds an excess of the part.

A3. Does pegging or reservation matter (PO lines showing Pegged = 0)?

For Project MRP the supply and demand that count are the ones tagged to the project activity (PPSA), so the first thing to confirm is that both PO lines and the material requirements are connected to WF1 and WF4. The pegging rules for project inventory versus standard inventory apply to dynamic order processing, so pegging the PO line to the demand is unlikely to change this result. It is quick to test on a copy of the data: peg one line, rerun, and compare the MTRs.

A4. Expected design or defect, and what gives a single MTR or none?

On the set-up described this is how a project PNG run is designed to work, since the cross-activity transfer is the point of the job. These are the levers, and what each one does:

  • Per-activity job: nets within each activity only, so no MTRs between WF0, WF1 and WF4.
  • Generate MTR for Planning Only on the PNG: changes the type of MTR created to Planning (instead of Transfer, Borrow or Payback). It does not stop the MTRs being planned, and it cannot be combined with Automatic MTR.
  • Excluded Parts on the activity: the part is left out of the calculation for that activity.
  • Within PNG In/Out on the PNG: controls part transfer between the activities in the same PNG, so it is worth checking how it is set.

A5. Second test: why WF0 to WF1 to WF4 instead of WF0 straight to WF4?

The same principle applies, since WF0's surplus is treated as available to the whole project and the plan is built across the activities together. To see why the route goes through WF1 rather than direct, rerun the same data three ways and compare: with different priority numbers on WF0, WF1 and WF4, with WF1 excluded for this part, and with the per-activity job.

Worth a look: the IFS Cloud documentation for Planned Netting Group (priority number, Within PNG In/Out, Generate MTR for Planning Only, Excluded Parts) and About Project MRP (netting per activity, per project PNG, per PNG).

What priority numbers do WF0, WF1 and WF4 have in the project PNG, and is the part excluded on any of them?

Created with the help of Ask Olive.