Here is my setup

I’ve got an activity with a start of 6/25 at 8 am and an end of 6/25 at 5 pm, it’s a 1 day duration and I have Resource 1 assigned for 1 hour on this day.

I also have Resource 1 assigned to a project connected work order for a 4 hour task planned for 6/25 8 am to 6/25 12 pm, hours.

When I select Resource Activity Load, I get the following, it is showing my Work Task planning, but it is not showing the planning of the activity resource itself.

Next, If I go to Resource Activity Load Detail, I get the following, it shows .82 hours even though I have it planned for 1 hr and it doesn’t show the plan for the Work Task.

I’m looking for help in understanding why these screens are like this and to understand how the system calculated .82 planned hours when I specified 1 hour on the activity’s resource plan. 

In addition, from the resource planning of the project, I see my 1 hour and 4 hour planned hours but when I select Resource Activity Load from this screen, I get nothing.

If anyone might offer an explanation for this too, I’m all ears.

/Patrick