Hi All,
I have this scenario what I cannot figure how to set-up and support, either in core or with a CRIM..
The customer has products, planned according MTO and use DOP in IFS for 6 levels.
The Top Product has a leadtime of 5 days and multiple operations.
The componets are connected to operations, planned demand spread over the 5 days routing.
All sub-assemblies and purchase parts are backward planned according to start date of each DOP Order Operation/Shop Order Operation.
Now to the issue.
I want all sub-assemblies to be planned the week before start date of the Top Shop Orders.
Equal “gap” between 1st level sub-assemblies to 2nd level sub-assemblies and so on.
I have multiple operations but one work center per level which means that I cannot use Queue time as the add queue time for all operations.
I cannot use off-set time as the compnents are and must be connected to operations.
I apprichiate any suggestions to solve this in core or by a clever CRIM.
Offcourse a manual solution exists but that doesn’t work in reality, as the costemer has 1000+ DOP Headers in the pipeline and up to 6 levels in the DOP Structure.
For purchase parts you can add internal lead time but not for manufactured sub-assemblies.
Transport time in sub-level routing is not an option due to the big number of routings and last operation differ depending on sub-assemble part.
It’s related to idea
https://community.ifs.com/ideas/7637