Skip to main content
Question

Parallel production in 1 operation

  • April 15, 2026
  • 0 replies
  • 27 views

Forum|alt.badge.img+6

Hi all, 

We are trying to model parallel production within a single shop order operation in IFS Cloud, and I would like to understand whether there is a standard solution for this.

Example (calculation will not be perfect, its just an example) :

  • 1 product
  • 1 shop order operation
  • shop order quantity = 26 pieces
  • all 26 pieces can be produced within 1 day
  • throughput time through the work center for 1 piece is 3 hours
  • the work center is staffed by multiple operators, all working in parallel on the same operation
  • currently, machine time is set to 3 hours and 1 labor resource is set to 3 hours

The issue is that IFS calculates the operation start and finish as if the full quantity is processed sequentially, which does not reflect the real situation.

I also tried increasing the work center efficiency to 1000% because there are 10 workplaces/operators available, but this did not change the operation lead time or the start/end time as expected.

What I want to achieve is:

  • one single operation
  • multiple pieces from the same shop order being processed in parallel within that operation
  • realistic operation start and finish times based on parallel capacity

What I do not want is:

  • splitting the operation into 10 separate parallel operations

Is there a standard way in IFS Cloud to model this correctly?

Any guidance or best practice would be appreciated.

Kind regards, 
Willem