Question

OEE, access and how it affects WC

  • 30 June 2023
  • 7 replies
  • 102 views

Badge +2

Hi IFS-community,

 

I have a question regarding the metric OEE. 

We have currently using IFS10, but are moving towards integrating IFS-Cloud later on this year.

 

Under what segment can I find the set-up documentation for OEE and how it works in IFS? More specifically, how it affects the capacity of our work centers.

 Best Regards

Anders


7 replies

Userlevel 6
Badge +20

About OEE
https://docs.ifs.com/ifsclouddocs/23r1/Manufacturing/AboutOEE.htm


Activity Diagram

Manufacturing > Shop Order Manufacturing Execution > Machine Monitoring and Performance - OEE
https://docs.ifs.com/ifsclouddocs/23r1/ProcessModels/Process_Model/MachineMonitoringandPerformance-OEE.htm

Badge +2

Thank you Matt, it seems that we do not yet have access to it.

Whereas it seems to be exclusive to IFS - Cloud. 

 

Do you know how the OEE affects the capacity in the WC or does it not?

Userlevel 6
Badge +20

Thank you Matt, it seems that we do not yet have access to it.

Whereas it seems to be exclusive to IFS - Cloud. 

 

Do you know how the OEE affects the capacity in the WC or does it not?

@Björn Hultgren any input on this?

Userlevel 7
Badge +23

The work center capacity is used in the calculation of OEE. But it does not effect the capacity as such. I'm not sure I fully understand the question I'm afraid. 

Badge +2

I´ll try to describe a scenario and we´ll see if I can make it easier to understand!

 

Lets say that we have a work center ( WC ) with resources attached to it.

Each of the resources have OEE associated with it ( maybe it is just on a WC - level and not separate ).

 

In month 1, the WC has an OEE of 75% with an plannable capacity at 8 hours. 

In month 2, the WC decreases the OEE to 50%, will the plannable capacity adjust when calculating the WC-capacity? Or is the OEE just a metric for the user to use as we please?

 

BR

Badge +1

About OEE
https://docs.ifs.com/ifsclouddocs/23r1/Manufacturing/AboutOEE.htm


Activity Diagram

Manufacturing > Shop Order Manufacturing Execution > Machine Monitoring and Performance - OEE
https://docs.ifs.com/ifsclouddocs/23r1/ProcessModels/Process_Model/MachineMonitoringandPerformance-OEE.htm

Morning Matt, 
Thank you for sharing the links however I’ve noticed that some of the info won’t work. Calculate OEE and OEE Calculations 
Any guess why is that? 

 


 

 

Userlevel 7
Badge +23

I´ll try to describe a scenario and we´ll see if I can make it easier to understand!

 

Lets say that we have a work center ( WC ) with resources attached to it.

Each of the resources have OEE associated with it ( maybe it is just on a WC - level and not separate ).

 

In month 1, the WC has an OEE of 75% with an plannable capacity at 8 hours. 

In month 2, the WC decreases the OEE to 50%, will the plannable capacity adjust when calculating the WC-capacity? Or is the OEE just a metric for the user to use as we please?

 

BR

Calculating OEE will not adjust any capacity parameters on the work center.,

Reply