Skip to main content

Hi IFS-community,

 

I have a question regarding the metric OEE. 

We have currently using IFS10, but are moving towards integrating IFS-Cloud later on this year.

 

Under what segment can I find the set-up documentation for OEE and how it works in IFS? More specifically, how it affects the capacity of our work centers.

 Best Regards

Anders

About OEE
https://docs.ifs.com/ifsclouddocs/23r1/Manufacturing/AboutOEE.htm


Activity Diagram

Manufacturing > Shop Order Manufacturing Execution > Machine Monitoring and Performance - OEE
https://docs.ifs.com/ifsclouddocs/23r1/ProcessModels/Process_Model/MachineMonitoringandPerformance-OEE.htm


Thank you Matt, it seems that we do not yet have access to it.

Whereas it seems to be exclusive to IFS - Cloud. 

 

Do you know how the OEE affects the capacity in the WC or does it not?


Thank you Matt, it seems that we do not yet have access to it.

Whereas it seems to be exclusive to IFS - Cloud. 

 

Do you know how the OEE affects the capacity in the WC or does it not?

@Björn Hultgren any input on this?


The work center capacity is used in the calculation of OEE. But it does not effect the capacity as such. I'm not sure I fully understand the question I'm afraid. 


I´ll try to describe a scenario and we´ll see if I can make it easier to understand!

 

Lets say that we have a work center ( WC ) with resources attached to it.

Each of the resources have OEE associated with it ( maybe it is just on a WC - level and not separate ).

 

In month 1, the WC has an OEE of 75% with an plannable capacity at 8 hours. 

In month 2, the WC decreases the OEE to 50%, will the plannable capacity adjust when calculating the WC-capacity? Or is the OEE just a metric for the user to use as we please?

 

BR


About OEE
https://docs.ifs.com/ifsclouddocs/23r1/Manufacturing/AboutOEE.htm


Activity Diagram

Manufacturing > Shop Order Manufacturing Execution > Machine Monitoring and Performance - OEE
https://docs.ifs.com/ifsclouddocs/23r1/ProcessModels/Process_Model/MachineMonitoringandPerformance-OEE.htm

Morning Matt, 
Thank you for sharing the links however I’ve noticed that some of the info won’t work. Calculate OEE and OEE Calculations 
Any guess why is that? 

 


 

 


I´ll try to describe a scenario and we´ll see if I can make it easier to understand!

 

Lets say that we have a work center ( WC ) with resources attached to it.

Each of the resources have OEE associated with it ( maybe it is just on a WC - level and not separate ).

 

In month 1, the WC has an OEE of 75% with an plannable capacity at 8 hours. 

In month 2, the WC decreases the OEE to 50%, will the plannable capacity adjust when calculating the WC-capacity? Or is the OEE just a metric for the user to use as we please?

 

BR

Calculating OEE will not adjust any capacity parameters on the work center.,


Reply