Not possible to expand APB capacity

  • February 23, 2023
  • 3 replies
  • 49 views

Forum|alt.badge.img+5

After adjusting the calendar to reflect overtime, re-generating and re-calculating capacity etc, the capacity shows up as available in the APB (see attached picture) but it is impossible to place any load on the time added - no matter if you’re doing a re-scheduling or manual drag-and-drop. If I use the manufacturing visualizer to drag-and-drop, the extra capacity is used so it’s just the APB that isn’t working. Version is App10, upd 13.

3 replies

Forum|alt.badge.img+5
  • Author
  • Do Gooder (Partner)
  • 14 replies
  • February 23, 2023

@Björn Hultgren - have you seen this behaviour?


Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+25
  • Hero (Employee)
  • 1061 replies
  • February 23, 2023

@AddMikaeA Unfortunately I have no insights in this.


Forum|alt.badge.img+5
  • Author
  • Do Gooder (Partner)
  • 14 replies
  • February 23, 2023

Found it, it was a labor class with infinite albeit separate schedule that interfered so that schedule needed adjustment as well.