Question

Non consumed parts included in capability check

  • June 16, 2021
  • 2 replies
  • 154 views

Heshani Jayawickrama
Hero (Employee)
Forum|alt.badge.img+6

When running capability check, are non-consumed components considered if qty per assembly>0, lead time>0? 

This topic has been closed for replies.

2 replies

Forum|alt.badge.img+9

@Heshani Jayawickrama 

 

As per my understanding this is the as design behaviour of the system. 

 

As a workaround you can exclude parts from capability check by changing the flag in product structure component line from "promised" to "not promised".


Praveen Wijetunge
Sidekick (Former Employee)
Forum|alt.badge.img+8
  • Sidekick (Former Employee)
  • 33 replies
  • June 25, 2021

Hi Heshani,

The application is designed in a way where the lead times of non-consumed parts are considered for capability check.

However, it is possible to exclude parts from capability check by changing the flag in product structure component line from "promised" to "not promised".

The value Not Promised will exclude this part and all associated component parts from the Capability Check used within IFS/Customer Orders.

 

Best Regards,

Praveen Wijetunge