A quick functional question related to DOP which I encountered with one of the customers.
Questions:
In APP9 DOP orders have the non-consumed items with the quantities. More specifically, unlike in APP8, when we bring in DOP structures in APP9, the structures come in with quantity for all non-consumed components.
Like your advice and view point on this regards.

1 reply

Userlevel 5
Badge +7
In IFSAPP9, main purpose of this change is to provide information to the user regarding the component requirement as defined in the product structure.
Hence in APP9 we recommend that to change the consumption of a Not Consumed part in the product structure itself (qty per assembly=0) if you do not want quantity in DOP structure for that particular part or if you still expecting APP7.5 behavior we have to execute a modification/customization (which is billable) to overcome this situation.
However in App9 if still you proceed with quantity for non-consumed components in a DOP structure and there will be not consumed in the material issue process for those component parts.