Hi All,
I am trying to get DDMRP working for a client in Apps10, but I seem to be missing something as I don’t see any data on ‘Demand Driven Execution for Parts’ window. Steps followed include;
1.Run Cumulative Lead Time calculation for the site.
2.Set the buffered parts.
3.Run Perform Lead Time Category Classification.
4.Run Calculate Historical Average Daily Usage.
5.Calculate buffer zones.
6.Manual adjustment to ‘ADU’ quantity (to make changes to calculations).
7.Recalculate buffer zones.
8.Run MRP for site.
9.Can see records in ‘Demand Driven Planning for Parts’ window.
But can’t see any records in ‘Demand Driven Execution for Parts’ window. So, what am I missing here? Any thoughts?