Missing code part checkbox in Project Resource Forecast

  • September 30, 2019
  • 1 reply
  • 289 views

Forum|alt.badge.img+8
When entering a Resource into a Project Resource Forecast, a warning is given that the Project Cost Revenue Element (PCRE) is mandatory.
After ignoring the warning,
looking at the Cost Element shows the PCRE has an entry.
However, the checkbox for missing Code Part remains which prevents further processing.

Best answer by Pabasara Kalahe

Hi Elath,

This is probably an issue related to the posting control. Ensure that the posting control is set up correctly for posting types PRJT1 and PRJT2. Pay special attention to control types such as PRJC1 and PRJC14. You can also add the default values for the relevant posting control line, if detailed setup is not required.

Hope this helps!
View original

Pabasara Kalahe
Hero (Employee)
Forum|alt.badge.img+7
Hi Elath,

This is probably an issue related to the posting control. Ensure that the posting control is set up correctly for posting types PRJT1 and PRJT2. Pay special attention to control types such as PRJC1 and PRJC14. You can also add the default values for the relevant posting control line, if detailed setup is not required.

Hope this helps!