Why am I not seeing the capacity on the Manufacturing Visualizer using the Labor Operation Load in Standard Hours, it shows the team Available Capacity. I believe it used to, not sure why I’m not seeing it. The work center has daily capacity in the time frame I’m looking. I have also tried it for another business that is machine drive and it doesn’t show for Machine Operation Load in Standard Hours. I have capacity in all workcenters.
Page 1 / 1
Hi,
Some things to try ...
Run the ‘Calculate the Labour Capacity’ for your site first.
Then run the ‘Perform CRP’ calculation for your site.
Search for your Labour Class and Site in the ‘Labor Load per Labor Class’ window - can you see values in the ‘Labor Capacity’ field?
If so, switch to the Mfg Viz view and take a look at the ‘Labor Operation Load in Standard Hours’ chart.
The capacity line should be shown.
Thanks Richard