Hi,
There is a WO for the Object connected to the Work Center Resource. However, the Maintenance Import job is not creating a Resource Break.
Cloud version

Data setup
Site enabled for APB

Object Connected to the WC Resource

WO/and Work Task are both for the same above Object

Task Site is the same

Duration, Planned Start/Finish dates are specified

Operational Status of the task object is “Obstructive”

Task status is “Released” (tried with “Started” as well)

Executed the Job


No Resource Break created for this WC Resource

Any idea what am I missing here ?