1, I created a new cost set (Cost Set 6) and assign M110 and  P110

 

  1. Then I calculated the  std cost for a Manufactured Part , non of the manufacturing related cost buckets were fetched

 

Any reason ?.

  1. When I calculated the std cost for the same part using cost set 2,cost was correctly calculated 

 

Application Version= IFS 10

 

Your prompt assistance, very much appreciated 

Have you added Cost Set 6 to your Work Centers and Labor Classes?


Hi Matt,

 

You are absolutely right. I did not.

 

Thank you very much for your superb answer.

 

BR

 