Is there a look-ahead parameter for Safety Stock Replenishment? How to Prevent Master Scheduling from Generating Additional Supply When Future Shop Order Supply Exists?

  • Nov 25, 2026 12:22 PM UTC
  • 1 reply
  • 20 views

Forum|alt.badge.img+6

Hello,

I have a master scheduled part with a safety stock defined.
Current situation:

  • On 16-Dec, Master Scheduling generates a Shop Order Requisition proposal because the projected on-hand quantity falls below the safety stock level.
  • However, on 17-Dec, there is already an existing shop order supply due, which replenishes the inventory and brings the projected on-hand quantity back above the safety stock level.

As a result, Master Scheduling creates an additional supply proposal even though a valid supply already exists shortly afterward, effectively resulting in excess or duplicated supply.

Is there a parameter or setting that allows Master Scheduling to look ahead a certain number of days when evaluating safety stock shortages, so that near-future supplies are considered before generating new replenishment proposals?

If so, which setting controls this behavior and how is it typically configured?

1 reply

Forum|alt.badge.img+5
  • Do Gooder (Employee)
  • Nov 25, 2026 4:04 PM UTC

Hi ​@KatarzynaPrae,

 

Based on my research - no. MS Level 1 in Apps 10 has no look-ahead or reschedule tolerance parameter for safety stock.

MS calculates the projected balance day by day. If the balance falls below safety stock on a day outside the Planning Time Fence, MS creates a proposal for that day. It doesn't check whether a supply due the next day would cover the gap, and it won't move your existing shop order earlier for you. So as far as MS is concerned, the December 16 proposal is correct.

The fix is in the data or the time fences:

1.Pull the shop order in. If the December 17 shop order can finish a day earlier, change its date to December 16 or earlier and re-run MS. Planned MS proposals outside the PTF are recalculated on every run, so the extra one should drop off.

2.If the proposal is already Fixed (it has crossed into the PTF), don't count on MS removing it. Check after the re-run and delete the requisition yourself if it's still there.

3.Review the Planning Time Fence on the MS Level 1 Part. Inside the PTF, MS doesn't create or change proposals. It only raises the "Projected balance is below safety stock" action message so the planner can decide. If you want near-term dips reviewed by a person rather than planned automatically, widen the PTF. The trade-off is more action messages to work through.

4.Check Create S/P Req. With "Create S/P Req Entire Horizon", every MS proposal becomes a shop order requisition right away. With "Create S/P Req", requisitions are only created inside the PTF. You see the MS proposal first and have time to adjust the existing shop order before a requisition appears.

 

To narrow it down, can you share your DTF and PTF values, your Create S/P Req setting, and whether the December 16 proposal shows as Planned or Fixed in the MS grid?

 

Hope this helps,

Gleb