How to add costs for non-consumed part is in part cost calculation (part cost)

  • 9 July 2021
  • 1 reply
  • 258 views

Userlevel 2
Badge +4

At our production site we need to pack parts before the leave production. Therefore, I would like to add a non-consumed part to the structure which holds a cost of 15, - euro to add cost for packing. When I recalculate the structure in cost set 5 I do see the part with its cost in structure multilevel tab but no costs are added to the level sales cost.

 

In which way can I add these costs?

 

icon

Best answer by matt.watters 9 July 2021, 15:42

View original

This topic has been closed for comments

1 reply

Userlevel 6
Badge +20

In Costing Basic Data > Cost Parameters, set INCLUDE_NOT_CONSUMED to Yes to include product structure components marked not consumed in Cost Rollup. Note this will lead to shop order variance if used in Cost Set 1 because not consumed parts are not included in shop order costs by definition.

Also, this will not add to Level Sales Cost, only to Total Sales Cost.