Hello all!

I want to add an Approval Process to Routings similar to Document Revision.  I have seen it done before but it was already enabled prior to me.  How do I enable this feature?  Thank you!!

 

 

Best answer by Roel van Zwieten

You can enable this on the ‘Object Connections’ screen. The online help should be able to guide you on how to set it up for the Routing screen.

https://docs.ifs.com/techdocs/foundation1/040_administration/220_user_interface/130_object_connections/default.htm

3 replies

Forum|alt.badge.img+14
  • Superhero (Employee)
  • 159 replies
  • Answer
  • October 25, 2022

You can enable this on the ‘Object Connections’ screen. The online help should be able to guide you on how to set it up for the Routing screen.

https://docs.ifs.com/techdocs/foundation1/040_administration/220_user_interface/130_object_connections/default.htm


anbouk
Superhero
Forum|alt.badge.img+16
  • Superhero
  • 225 replies
  • October 25, 2022

Rob,

Here is a link to a post where there are instructions to not just enable the approval process, but to automatically add it based on criteria, and prevent the object from being released/approved etc until the approval process has been completed…

Set up of Approval routing IFS App9 | IFS Community

Good luck,

Antony


Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • 1 reply
  • October 26, 2022

Thank you both!  The info provided by Roel got me what I needed!