How does the aeam access supercede in Projects for multiple teams for one team member?

  • 4 August 2021
  • 2 replies
  • 109 views

Userlevel 5
Badge +10

In a scenario where a team member is in 2 teams where one has view only permission and the other has access to change time, cost and material in the project, which team access is in effect for that particular team member?

icon

Best answer by Tharindu Fernando 4 August 2021, 08:02

View original

This topic has been closed for comments

2 replies

Userlevel 5
Badge +8

Hi Dasuni,

In this scenario, the team with the higher access capabilities is given priority; i.e. the team with less or no restrictions.

/Tharindu Fernando

Userlevel 5
Badge +10

Thanks @Tharindu Fernando