How does the aeam access supercede in Projects for multiple teams for one team member?

  • August 4, 2021
  • 2 replies
  • 132 views

Dasuni Samarakoon
Hero (Employee)
Forum|alt.badge.img+10

In a scenario where a team member is in 2 teams where one has view only permission and the other has access to change time, cost and material in the project, which team access is in effect for that particular team member?

Best answer by Tharindu Fernando

Hi Dasuni,

In this scenario, the team with the higher access capabilities is given priority; i.e. the team with less or no restrictions.

/Tharindu Fernando

This topic has been closed for replies.

2 replies

Tharindu Fernando
Hero (Employee)
Forum|alt.badge.img+8
  • Hero (Employee)
  • 14 replies
  • Answer
  • August 4, 2021

Hi Dasuni,

In this scenario, the team with the higher access capabilities is given priority; i.e. the team with less or no restrictions.

/Tharindu Fernando