Hi @matt.watters ,
For Level 0,
Total Est Level Cost = Level Cost of part for the specific cost bucket in level 0 (i.e. Level Cost/Unit column shown in Order Cost Estimates tab in the Shop Order Costs window)
For Levels > 0,
Total Est Level Cost = Cost Qty per Assembly * Accum Cost of part for the specific cost bucket in that specific level
Cost Qty per Assembly is shown in the Estimated Details tab in Shop Order Costs window. I could not find a window which is showing shop order specific Accum Costs for levels > 0. You can get that value from the Part Cost window I guess.
For By-Products, the calculation is same as described in levels > 0 section above.
This is how it calculates in code level. Hope this helps.
This is quoted from the below thread. Please refer to it for further information
How the Total Est Level Cost is calculated in shop order estimated cost? | IFS Community
Best Regards,
Charana