Hello,
We have a question regarding fulfillment dates and feedback loops.
- We create a customer order for an item and put a planned ship date of 3 days from today
- Site MRP is run later and determines we will need to build the item and manufacturing lead time (and purchasing lead times) dictate it will take 3 weeks to build
Is there a mechanism in IFS that will alert (or modify) the original customer order that the original date is no longer feasible? Or are custom events or reports the only method?