I am encountering the following error while launching the IFS standard functionality Change Rev Alt via a scheduled task that allows to update the Routing and/or Structure from a chosen DOP order in the DOP structure.
 

I tried to add the resource in the Work Center and relaunch the batch, but I am still encountering the same issue.

T tried to launch the function online from the DOP Order, but the structure is too complex and after 10 minutes I encounter an error.

Do you have any idea? 
Thank you!

I think after changing the revision, the start date is calculated based on the changed revision, then the work center resource may not be available for this Start Date.

If you change the Due Date to a date far in the future or reduce the Demand Qty (Or both) would probably move the calculated start date to a date where the Work Center Resource is available, 

Alternatively, you can try to Set the resource start date in the Work Center to a date something very early so that the Resource is available on the calculated Start Date. 

Also just to make sure just add small Setup Time in the Operation in the new alienate (Run time =0) also would help to identify if the cause is due to the calculated Start Date.