- I have a work order where the Dept is populated for Pre Posting.
- I try to connect the work order to a project activity
- After entering the project activity data, I click on the OK button and get the following error message and the activity is not connected.
- When I open the Pre Posting window, there is a Dept entered.
- What do I need to do to connect the activity to the work order? (we are using IFS 9)