Hi,

When we do Engineering Revision Transfer the Product Structure Status is default “Tentative”. Is there a way to set the DEFAULT status for manufactured parts (Structure Type = Manufacturing) to Buildable? Or at least a way to update the status for all new transferred manufactured parts?

Best regards,
Anita

icon

Best answer by AanHGTS 6 September 2021, 10:54

View original

This topic has been closed for comments

5 replies

Userlevel 5
Badge +12

No I don’t think you can do during Engineering Revision Transfer. 

But you may write a Customer Event to set to Builable.

And you may try Multilevel Promotion too.

Userlevel 2
Badge +4

Thank you for your reply! 
Best regards,
Anita

Userlevel 5
Badge +12

@ANBR After Engineering Transfer you can use the “Structure Alternates” window and query the newly transferred and make then Buildable. 

 

 

Userlevel 2
Badge +4

Thank you! This column I have missed. :-)

With some help we have now have created a Custom Event and it works fine.

Best regards Anita

Badge +2

You could set a default for this at the site level, but I don’t believe this differentiates between Manufacturing and Purchase structures. I also don’t know whether it will status the Routing.