Is there an option to set an Engineering Revision not to transfer until the Revision status is Released? There is no other way to check whether Approval completed, all required documents is attached, etc. before the transfer.

Best answer by anbouk

Hi,

I am not aware of anything in this area to prevent the transfer, so the only option would be to create a custom event to check status=”Released” etc before allowing the action to take place.

2 replies

anbouk
Superhero
Forum|alt.badge.img+16
  • Superhero
  • 225 replies
  • Answer
  • December 11, 2019

Hi,

I am not aware of anything in this area to prevent the transfer, so the only option would be to create a custom event to check status=”Released” etc before allowing the action to take place.


Sumedha
Sidekick (Partner)
Forum|alt.badge.img+6
  • Author
  • Sidekick (Partner)
  • 21 replies
  • December 12, 2019

Hi,

 

Yeah, I too see that is the only option available for the moment.Thank you for the reply.