We have a requirement to apply dual sourcing through the product structure: two different but interchangeable components that should be used in, for example, a 50/50 ratio.
Using phase in/phase out doesn’t seem like a good solution, because shifting schedules cause new purchase requisitions to move from product A to product B within the lead times.
Dual sourcing via Purchasing isn’t possible either, because the two components are physically different items and therefore must be procured as separate components.
Does anyone have a suggestion on how this could be handled within standard IFS Cloud?
Thanks in advance!
Best answer by Richard Owen
Hi,
Perhaps you can consider setting it up with a new phantom part for a ‘dual-source kit’?
Can you not have both the components in the product structure and at the shop order level you can delete the not required component? Explore this option if it is feasible