Hi,
The default setting for ‘DOP pegged SO update’ (Inv part - manufacturing tab) is “Planned”. For parts with the supply type “Requisition”, this can not be changed to “Released”.
If I make a DOP with full level settings, i get pegged shop orders after netting and releasing (assuming I don’t have stock). Also for parts with the supply type “Requisition”. I want to update these shop orders if they are in released status, however due to the setting above I cannot do this: I first need to go to all DOP orders and change the setting there to overrule the setting on inventory part.
This is very time consuming in large DOP structure. Is there a faster way to change this for every part?