Question

DOP - mass update date and/or revisions

  • Sep 15, 2026 5:24 AM UTC
  • 1 reply
  • 32 views

Forum|alt.badge.img+7

Hi,

We have a use case according to following

Customer order is released for a high volume of COL, for example 2000 products. The product is ETO but all has the same BOM revision. The COL’s are connected to project for financial and other reasons and qty for each line is 1. This results in 2000 COL and 2000 DOP Headers and the delivery time for the lines are spread over 12-24 month. 
 

Challenge/Problem:
The Customer Order is released and lines connected to project activities. MS Level 1 cannot be used to create supply for non-DOP parts.
The DOP structure must be created for all DOP’s, if not created = no demand for non-DOP parts. 

Please confirm that this is correct, I might missed something:
1. Unreleased CO is a demand and MRP create supply for non-DOP parts (Released for Mtrl Planning enabled)
2. Released CO, DOP Header created, this is a demand but MRP doesn’t create supply for non-DOP Parts
3. Released CO, DOP Header created and Top DOP Created, this is a demand but MRP doesn’t create supply for non-DOP Parts
The site parameter for “Allow MRP Explosion of DOP Parts” is not considered in above cases.

According to the above scenario, we must have released CO and we must create DOP Structure for all 2000 products, to ensure supply of non-DOP parts. 

Now the normal use case. 
Delivery date change and replanning of production needed. 
Date must be changed manually, one by one for 2000 CO lines or DOP Headers, after that Top DOP Date must be updated manually for 2000 DOP Orders, one by one, after that Propagate Date Up-streams must be done for 2000 Top Dop Orders, one by one. 

The other normal use case is that a new structure revision is released. 
As all DOP Structures are created, update revision must be done for 2000 DOP structures, one by one.


Anybody who has a good solution for this?
Ideas, can the flag “Allow MRP Explosion of DOP Parts” also consider DOP Headers, Top DOP Orders without structure, not MS level 1 only and CRP can be run together with MRP?
In that case, we doesn’t need to create structures for 2000 lines from start and can create structures for coming production planning time fence only.
Can we update Dates for Multiple records, by using offset from existing date?
Can we run standard functions as Update Top Order Date, Propagate Date/Qty and/or change revision for multiple records?

All ideas and solutions in this tricky area is appriciated?
Is there anything in the R&D pipe line to support this or is there a solution in 25R2 I have missed?

​​​​​​​

1 reply

richardwoods
Do Gooder (Partner)
Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • Nov 25, 2026 2:17 PM UTC

Short answer: the work splits into pieces that already exist as standard commands, and the alarm route is the one to try first for date changes. The flag you mention is also worth a second look, because it lives in two places and the part-level one is on Master Schedule Level 1.

On the "Allow MRP Explosion for DOP Parts" flag

It is a site setting on Site / Manufacturing, in the Planning Settings section of the General tab, and it applies when the DOP parts are planned by master scheduling. There is also an Allow MRP Explosion for DOP Part option on the Master Schedule Level 1 Part page, which makes MRP explode through the default manufacturing structure and propose the non-DOP parts, based on the netted MS proposals.

Dates: a route that avoids the one-by-one work

  • Change the delivery date on the customer order line. A mismatch between the line and the DOP header raises an alarm, listed on DOP Alarms (Manufacturing > Dynamic Order Processing > Order).
  • From the alarm, Update DOP Header Due Date aligns the DOP header and the top DOP order with the customer order line. That removes the separate manual edit of the header and the top order.
  • If the top DOP order is out against the header, Update Top Level Date (Update Date/Quantity menu on the DOP header) moves the top order to the header date. It asks whether the pegged supply orders should follow, and if you say no, time alarms can appear.
  • Then Propagate Date Upstream (Propagate Date/Quantity menu on DOP Order or DOP Orders) moves the child levels, based on the due date of the order you run it from.

New structure revision

On DOP Order, Change Structure/Routing, then Change Revision and/or Alternate, opens the Change DOP Structure/Routings dialog. The old structure is removed and the new one added, so it is worth trying on one order first. The DOP header needs Allow Changes to DOP Structure enabled, and the order should be Unreleased or Released.

Things to know

  • Create/Update Structure in Background on the same site page is aimed at very large structures, but it does not cover structures created when a customer order is released, so do not count on it for your 2000 lines.
  • Structure Depth on the DOP header (DOP Parts or Full Level) decides how many DOP orders are created per line, which matters when you multiply by 2000.
  • The structure only needs to exist for the part of the horizon you want supply for, so creating DOP structures just for the coming planning window is a reasonable operating pattern, as long as non-DOP supply for later lines is not needed yet.

Worth a look: the IFS Cloud documentation for Update Top Level Date, Propagate Date Upstream, Change DOP Revision/Alternate, Update DOP Header Due Date and Configure DOP Settings for Site. Also try the commands with several rows selected on DOP Orders and DOP Alarms to see which ones take a multi-row selection in your version.

Which release are you on, and are the 2000 lines released in one go, or in batches by planning window?

Created with the help of Ask Olive.