Question

DOP Challenges

  • 1 March 2024
  • 2 replies
  • 40 views

Userlevel 1
Badge +6

Hi Experts

Seeking your inputs on the below DOP challenges.

  1. Currently DOP doesn’t allow to create a Request for Quotation from the generated PR’s, this block the Quotation Process. 1A. What is the reason for this ? 1B. What is the alternative to create a RFQ within DOP.
  2. DOP Netting Has 3 Different Options, Inventory , Dop Sourced and Invontory Sourced. 2A. In What sequence the Reservation takes place when all the 3 are Enabled. 2B. Do we have any set up to change the sequence of Netting when all the 3 are enabled.

You input will greatly helps.

Thanks !

 

Regards

Lokesh


2 replies

Userlevel 1
Badge +6

Hi @Björn Hultgren, Any thoughts on this

Userlevel 7
Badge +23

Not sure why request for quotation is not enabled for a DOP generated PR. Guess it has never been prioritized. 

The netting  is using the priority sequence as documented in the netting activity below:

 

Reply