DDMRP how I can calculate "calculated ADU Qty"

  • September 29, 2021
  • 2 replies
  • 131 views

Forum|alt.badge.img+3
  • Do Gooder (Employee)
  • 3 replies

Hi together,

I have tried to do calculate this value (Calculated ADU Qty) with the job “Calculate Historical Average Daliy Usage”, but without success!

I have seen in window “Average Issues/Receipts per Period” that only 2 movements have taken place in the last 2 months.


Can somebody help me?
It is urgent.

 

BR
​​​​​​​Milanko

Best answer by majose

Hi,

Is the part connected to a lead time category with short rolling time fence horizon?

Can you start running some issue transactions for the parts today. Then they should be considered when you calculate ADU tomorrow.

Good Luck,

Mats

This topic has been closed for replies.

2 replies

Forum|alt.badge.img+14
  • Hero (Employee)
  • 308 replies
  • Answer
  • September 29, 2021

Hi,

Is the part connected to a lead time category with short rolling time fence horizon?

Can you start running some issue transactions for the parts today. Then they should be considered when you calculate ADU tomorrow.

Good Luck,

Mats


Forum|alt.badge.img+3
  • Author
  • Do Gooder (Employee)
  • 3 replies
  • September 29, 2021

Hi Mats

Thank you for the input, I will try to do that today!

And I hope I have tomorrow the success :-)

Thanks and best regards
Milanko