We have around 10 sites all running in same database.
All jobs like MS, MRP and CRP needs to be run daily due to our line of business.
We now run in to issues that the “night window” is getting too small and jobs are not ready in time in the morning.
Especially the CRP is taking very long time to run for some sites, up till 90 minutes.
Does anybody know what is impacting the CRP execution time the most?
Is it the number of workcenters in use, or the number of shoporder requisitions in the system (master schedules set to create sp for entire horizon) or a combination.
Any advise on this would be appreciated.