i have created a new work centre and ran CRP but keep getting the same ERROR message
ShopOrderScheduler.NOAVAILABLERESOURCECRP: No resource available on work centre PW4P1 when scheduling load source and order MRP/50168738/*/ operation 50 with finish date 20/07/2022.
i have tried to change the Start date of the resource capacity from the resource navigator but get anther ERROR message (below) caused by operations loaded in this timespan. cannot delete!
How do i resolve this issue?
regards
Jamie