Hi,

 

We have set up the Master Schedule module to create forecasts for manufactured parts related to Configuration Structures.

MRP correctly goes through all the levels of the structure for material requirements calculation.

 

We expected the same behaviour for the CRP process for labor, but we have noticed that only the first level of the Configuration Structure is taken into account by CRP for the Master Schedule source (it works correctly for Shop Order or DOP sources).

 

 

Are there any known limitations or particular setup requirements?

 

Thank you in advance.

IFS Current version : 25R2 SU5

1 reply

majose
Hero (Employee)
Forum|alt.badge.img+15
  • Hero (Employee)
  • October 27, 2026

Hello ​@Guillaume GARNIER 

Are all of your sub-assemblies DOP-planned more or less? Do you have any Shop Order Requisitions generated from MRP at all?

The configured parts are treated as P-phantoms in the MRP explosion logic - we don’t create Shop Order Reqs for these parts.

Can you give us some more information, coz this is interesting.

Thanks and Best Regards