in IFS10 IEE it is possible to create work order direct from project activity. Does Aurena have the same functionality?

Hi,

in IFS10 IEE it is possible to create work order direct from project activity. Does Aurena have the same functionality?

Yes, from Activity Resource Planning you can choose ‘New Work Order. You can get to that page from the navigator or from Activity Scope and Schedule → Materials and Services.

 



 

 


Great, thank you for quick reply :-)