Skip to main content
Question

Creating work order from project activity in Aurena

  • October 8, 2020
  • 2 replies
  • 119 views

Forum|alt.badge.img+2

Hi,

in IFS10 IEE it is possible to create work order direct from project activity. Does Aurena have the same functionality?

2 replies

  • Superhero (Employee)
  • 1495 replies
  • October 8, 2020

Hi,

in IFS10 IEE it is possible to create work order direct from project activity. Does Aurena have the same functionality?

Yes, from Activity Resource Planning you can choose ‘New Work Order. You can get to that page from the navigator or from Activity Scope and Schedule → Materials and Services.

 



 

 


Forum|alt.badge.img+2
  • Author
  • Do Gooder (Customer)
  • 1 reply
  • October 9, 2020

Great, thank you for quick reply :-)