When calculating items costs in the background, item costs are calculated only for the structure alternative * and routings *. Is it possible to set all other alternatives to be calculated as well?

Thank you in advance

Hi @CdcPatrCs,

You can navigate to Part Costs window and select all structure and routing alternatives related to the part, then RMB- Cost Calculation- Calculate Cost for Selected Parts. From this method you can calculate the costs related to all alternatives. 

 

/Buwaneka 