connection of DOP components to operations - planning

  • December 2, 2025
  • 1 reply
  • 24 views

Forum|alt.badge.img+5

Extending functionality on DOPs – connection of DOP components to operations – mentioned in 25R1. We have SU 25.1.2 + APB released on 2025-01-20. See behavior, seems does not work correctly:

DOP – 3 levels, component T-2 is connected to Operation 20 of T-1.
 

The same connection on SO:

APB before scheduling – just scheduler by IFS – OK

Parameters of scheduling in APB:

After scheduling in APB – connection to operation 20 ignored:

 

 

 

Thanks in advance.

 

 

1 reply

Forum|alt.badge.img+10
  • Hero (Employee)
  • December 9, 2025

The said development is focused on the scheduling by the DOP,