Skip to main content
Question

Connect Material requisition to a project

  • May 31, 2024
  • 2 replies
  • 99 views

Forum|alt.badge.img+7
  • Sidekick (Partner)
  • 51 replies

Hi All,

It is much appreciated if anyone can guide me to connect the material requisition to a project activity. Currently I am facing below error when I try to add project connection details(RMB option) manually.

Thanks in advance,

Theja

 

2 replies

Marcel.Ausan
Ultimate Hero (Partner)
Forum|alt.badge.img+22
  • Ultimate Hero (Partner)
  • 1306 replies
  • May 31, 2024

@Thej I just tested this functionality in 23R2 and it works without issues.

A couple of thigs I would check:

  • make sure that the activity you wanna connect to the Mat Req is Released and Project is started
  • make sure M107 for Project code part with AC2 (preposting) is enabled for your company

Buddhika Kurera
Superhero (Employee)
Forum|alt.badge.img+15
  • Superhero (Employee)
  • 388 replies
  • May 31, 2024

@Thej For your project please check if the values are set as follow under the Manual Connection. This should be the case most of the time. Change it accordingly so that you would be able to connect the Mat Req Line manually to the activity.