Hi,

 

I would like to move several operations from one workcenter to another. These operations are from different shop order, but should stick together:

 

I tried with operation blocks, but it doesn’t seem possible to just change the workcenter of the complete block? Is it?

 

Thanks!


This topic has been closed for comments

3 replies

Userlevel 7
Badge +23

Unfortunately this is not possible. It is possible to rescheduled an operation block to another resource within the same work center, but not between different work centers.

Userlevel 6
Badge +11

Thanks! So we need to disconnect and connect to the other operation block? Or do you see an easier way?

Userlevel 7
Badge +23

Yes, you must disconnected the operations from the block (and possibly delete it), then you must change the work center on the operations, and finally create a new operation block on this work center and then connect the operation to it.