Is there a way to update Change Request when connected CO in Approved state ?
Or What is the method to get the Change Order from Approved to Preliminary or Analyzed
Engineering>PDM>Change Management
Hi Guys,
Is there a way to update Change Request when connected CO in Approved state ?
Or What is the method to get the Change Order from Approved to Preliminary or Analyzed
Engineering>PDM>Change Management
Hi,
When the state of the CO is changed to Approved, the state of all the connected CRs will automatically be changed to Processed.
When a CR goes into Processed state, that means a CO has been issued for this CR.
Once the status is updated, the status change is irreversible.
Hope this helps.
/Pabs