Hello,
As I understand it, when I create and save a schedule using the Advanced Planning Board (APB), the updated planning dates are stored in the IFS database.
However, it appears that when the planner opens IFS the following (next) day, the schedule that was saved in APB has been overwritten, as if the Infinite Scheduler has run and recalculated the planning dates.
I would like to understand:
- Is there a way to freeze or firm the schedule created in APB so that it is not overwritten by the Infinite Scheduler?
- If no changes have been made to the affected shop orders overnight, what could trigger the Infinite Scheduler to reschedule them?
- Could this be caused by an MRP run, or are there any other background processes that can automatically trigger rescheduling?
Any guidance on how APB schedules are protected from automatic rescheduling would be greatly appreciated.