Skip to main content
Solved

Calendar connected to the production line

  • June 19, 2025
  • 1 reply
  • 57 views

Forum|alt.badge.img+5

Hello,

I have a question regarding the Production Line. Why is the production line connected to the calendar as it is already set up for work center? 
What would happen if I put an “empty calendar” for the production line and the right one is correctly connected for the work center? What would be the impact?

Thank you!

Best answer by matt.watters

The calendar for the Production Line works in conjunction with the Schedule Horizon connected to each production line part to establish past due dates, firm schedule receipts, and the schedule horizon used in any planning calculations.

1 reply

matt.watters
Ultimate Hero (Partner)
Forum|alt.badge.img+26
  • Ultimate Hero (Partner)
  • Answer
  • June 19, 2025

The calendar for the Production Line works in conjunction with the Schedule Horizon connected to each production line part to establish past due dates, firm schedule receipts, and the schedule horizon used in any planning calculations.