When a project date of end is extended, the demand's required date is also updating on its own. As per the definition of “Required Date” this is updated automatically. Is there a way to modify this set up to not be updated as such?
Page 1 / 1
Hi
“Required Date” definition is as such that the field is automatically changed in the standard application.
Required Date = “The date on which the miscellaneous demand is required. The required date for the miscellaneous demand is the early finish date for the connected activity minus the offset. This field is automatically updated when the early finish date of the activity or the offset is changed.”
Currently there is no such functional set up but a customer could opt for a customization in order to do so.
Regards,
Dasuni